The City of Buckeye is tentatively approved for a nearly $820 million budget —no more, maybe less. City Council’s May 20 vote approving the tentative fiscal year 2025-2026 budget is one step toward final approval on June 3.
This year's budget includes General Obligation Bond proceeds, paving way for anticipated projects that residents approved in the Nov. 5 election. Now that the tentative budget is adopted, Council may not exceed the $819.9 million amount, though it made reduce that total in future hearings.
Revenue Sources
Expenditures
Personnel Changes
The tentative budget proposed several updates to city personnel:
- Sixty-seven new city positions to be created
- 2.5% cost of living adjustment for the first pay period of the year
- 1% city deferred compensation contribution for all employees
- 4% merit increase for non-represented or non-public safety staff
- 5% merit increase for represented public safety staff, who make up 41% of the city work force
Capital Improvement Projects
The city's total five-year Capital Improvement Plan is budgeted for $745.4 million, $277.2 of which will be utilized in FY2025-2026. Notable projects include:
- $13.9 million for public safety projects:
- Police communication center
- Police Verrado Marketplace tenant improvements
- Victory Fire Station #709 design
- Westpark Fire Station #706 design
- $109.3 million for streets and transportation
- Jackrabbit Trail improvements
- Miller Rd. improvements
- SR-85 traffic signals
- $16.9 million for airport improvements
- Airport land acquisition
- Other improvements
- $104.6 million for wastewater and water
- White Tanks recovery well
- Wastewater improvements to facilities in Sundance, Festival and Central neighborhoods
- Jackie Meck Water Campus expansion
- North Airport Water Campus expansion
- Valencia Water System upgrades
Next Steps
Now that the tentative budget is approved, the budget will see a second publication on May 24. It will be brought before Council again on June 3 for a public hearing and final adoption vote.
Read the full city budget HERE.
2 Responses
The airport, why are we sinking that kind of dollars into a airport for only local use. That money should be allocated toward a better resource , such as speeding up the infrastructure around west buckeye and Watson and miller roads , the volume of residents is increasing way to fast and the roads are over loaded. As you can clearly see at miller rd. Seems to me we waited to long for anything to happen and the residents pay the price. Shouldn’t take 45 minutes to get to the freeway , when normally under 5 minutes.
Airport projects are funded primarily through grants from the FAA and ADOT. The city has to budget for the entire amount, though the City is only contributing a small portion of the total cost.